Skip to main content
Install and maintain

Complete the AFX system setup for the Cisco Nexus 9808 switch

Contributors netapp-yvonneo netapp-jsnyder

After completing Cisco Nexus 9808 switch configuration, power on the storage shelves and controllers, verify switch connectivity, and complete the AFX 2K system setup.

Before you begin
  • You must have completed the switch configuration procedures in the configure switch workflow.

  • Each switch must be connected to a console or you must have remote access to each switch.

Step
  1. Complete the power on and setup steps for your AFX 2K system by using the Power on your AFX 2K storage system procedure.

What's next?

After you've powered on the storage shelves and controllers and completed the AFX 2K system setup, you are ready to use your AFX system.