Connect the cables

Contributors netapp-echurch netapp-driley NetAppZacharyWambold netapp-jsnyder

Learn how to attach the power cables and power on the drive shelves.

Before you begin
  • Install your hardware.

  • Take anti-static precautions.

This procedure applies to IOM12 and IOM12B drive shelves.

Note IOM12B modules are only supported on SANtricity OS 11.70.2 onward. Ensure your controller's firmware has been updated before installing or upgrading to an IOM12B.
Note This procedure is for like-for-like shelf IOM hot-swaps or replacements. This means you can only replace an IOM12 module with another IOM12 module or replace an IOM12B module with another IOM12B module. (Your shelf can have two IOM12 modules or have two IOM12B modules.)
Steps
  1. Cable the shelves.

    Cable the system according to your configuration. If you need more cabling options than the examples shown, see Cabling.

    For the examples shown, you need the following cables:

    SAS cable

    SAS cables

    Example A: E5700 controller shelf with three DE212C/DE224 disk shelves in a standard SAS configuration.

    E5700 controller in a SAS configuration

    1. Cable controller A to IOM A of the first drive shelf.

    2. Cable IOM A of the first drive shelf to IOM A of the second drive shelf.

    3. Cable IOM A of the second drive shelf to IOM A of the third drive shelf.

    4. Cable controller B to IOM B of the third drive shelf.

    5. Cable IOM B of the second drive shelf to IOM B of the third drive shelf.

    6. Cable IOM B of the first drive shelf to IOM B of the second drive shelf.

    Example B: An E5700 controller shelf with one DE212C/DE224 disk shelf in a standard SAS configuration.

    E5700 controller in a SAS configuration

    1. Cable controller A to IOM A.

    2. Cable controller B to IOM B.

  2. Power the drive shelves.

    You need the following cables:

    Power cables

    Power cables

    Caution Confirm the drive shelf power switches are off.
    1. Connect the two power cables for each shelf to different power distribution units (PDUs) in the cabinet or rack.

    2. If you have drive shelves, turn on their two power switches first. Wait 2 minutes before applying power to the controller shelf.

    3. Turn on the two power switches on the controller shelf.

    4. Check the LEDs and seven-segment display on each controller.

      During boot, the seven-segment display shows the repeating sequence of OS, Sd, blank to indicate the controller is performing start-of-day processing. After the controller has booted up, the shelf ID is displayed.