Managing report schedules

Contributors

You can manage your report schedules from the Manage Report Schedules dialog box. You can add a new schedule and view, modify, or delete existing schedules.

Steps

  1. In the left navigation pane, click Reports, and then click Manage Report Schedules.

  2. In the Manage Report Schedules dialog box,

    If you want to…​ Then…​

    View or modify an existing schedule

    1. Select the schedule from the list displayed in the left pane.

      The schedule details are displayed.

    2. Make the necessary changes.

    3. Click Save or Save and Close.

    Delete an existing schedule

    1. Select the schedule from the list displayed in the left pane.

      The schedule details are displayed.

    2. Click Delete Schedule.

    Add a new schedule

    1. Click Add Schedule.

    2. A new schedule form appears in the right pane.

    3. Enter the schedule name, recipient email address, report format and frequency and select the reports you want to schedule.

    4. Click Save. The new schedule will be added in the Schedules list.