Skip to main content
Install and maintain

Hot-add an NS224 shelf to your ASA system

Contributors netapp-jsnyder

Follow these workflow steps to hot-add an NS224 shelf to your ASA system.

Before you begin

Verify that your ASA system meets the requirements for hot-adding an NS224 shelf, including ONTAP version support, number of shelves, and cabling requirements.

Depending on your platform model, you might need to install additional RoCE-capable PCIe cards or I/O modules, configure the non-dedicated RoCE-capable Ethernet ports for storage use, recable an existing shelf across two sets of ports in different slots for resiliency against slot failure, and disable automatic drive assignment if you are manually assigning drive ownership.

Install the rail kit for the shelf, install and secure your shelf in the telco rack or cabinet, connect the power cords to power on the shelf, and assign a unique shelf ID to ensure the shelf is distinct within the HA pair.

Cable the shelf you are hot-adding so that it has two connections to each controller in the HA pair.

If you disabled automatic drive assignment as part of the preparation for the hot-add, you need to manually assign drive ownership and then reenable automatic drive assignment, if needed.