Skip to main content
Install and maintain

Shut down the controllers - AFF A300

Contributors netapp-martyh

You must shut down the controllers before replacing the chassis.

Option 1: Most configurations

To shut down the impaired controller, you must determine the status of the controller and, if necessary, take over the controller so that the healthy controller continues to serve data from the impaired controller storage.

About this task
  • If you are using NetApp Storage Encryption, you must have reset the MSID using the instructions in the Returning SEDs to unprotected mode.

  • If you have a SAN system, you must have checked event messages (cluster kernel-service show) for impaired controller SCSI blade. The cluster kernel-service show command displays the node name, quorum status of that node, availability status of that node, and operational status of that node.

    Each SCSI-blade process should be in quorum with the other nodes in the cluster. Any issues must be resolved before you proceed with the replacement.

  • If you have a cluster with more than two nodes, it must be in quorum. If the cluster is not in quorum or a healthy controller shows false for eligibility and health, you must correct the issue before shutting down the impaired controller; see Synchronize a node with the cluster.

Steps
  1. If AutoSupport is enabled, suppress automatic case creation by invoking an AutoSupport message: system node autosupport invoke -node * -type all -message MAINT=number_of_hours_downh

    The following AutoSupport message suppresses automatic case creation for two hours: cluster1:> system node autosupport invoke -node * -type all -message MAINT=2h

  2. Disable automatic giveback from the console of the healthy controller: storage failover modify –node local -auto-giveback false

    Note When you see Do you want to disable auto-giveback?, enter y.
  3. Take the impaired controller to the LOADER prompt:

    If the impaired controller is displaying…​ Then…​

    The LOADER prompt

    Go to the next step.

    Waiting for giveback…​

    Press Ctrl-C, and then respond y when prompted.

    System prompt or password prompt

    Take over or halt the impaired controller from the healthy controller: storage failover takeover -ofnode impaired_node_name

    When the impaired controller shows Waiting for giveback…​, press Ctrl-C, and then respond y.

Option 2: Controllers are in a two-node MetroCluster

To shut down the impaired controller, you must determine the status of the controller and, if necessary, switch over the controller so that the healthy controller continues to serve data from the impaired controller storage.

About this task
  • If you are using NetApp Storage Encryption, you must have reset the MSID using the instructions in the "Return a FIPS drive or SED to unprotected mode" section of NetApp Encryption overview with the CLI.

  • You must leave the power supplies turned on at the end of this procedure to provide power to the healthy controller.

Steps
  1. Check the MetroCluster status to determine whether the impaired controller has automatically switched over to the healthy controller: metrocluster show

  2. Depending on whether an automatic switchover has occurred, proceed according to the following table:

    If the impaired controller…​ Then…​

    Has automatically switched over

    Proceed to the next step.

    Has not automatically switched over

    Perform a planned switchover operation from the healthy controller: metrocluster switchover

    Has not automatically switched over, you attempted switchover with the metrocluster switchover command, and the switchover was vetoed

    Review the veto messages and, if possible, resolve the issue and try again. If you are unable to resolve the issue, contact technical support.

  3. Resynchronize the data aggregates by running the metrocluster heal -phase aggregates command from the surviving cluster.

    controller_A_1::> metrocluster heal -phase aggregates
    [Job 130] Job succeeded: Heal Aggregates is successful.

    If the healing is vetoed, you have the option of reissuing the metrocluster heal command with the -override-vetoes parameter. If you use this optional parameter, the system overrides any soft vetoes that prevent the healing operation.

  4. Verify that the operation has been completed by using the metrocluster operation show command.

    controller_A_1::> metrocluster operation show
        Operation: heal-aggregates
          State: successful
    Start Time: 7/25/2016 18:45:55
       End Time: 7/25/2016 18:45:56
         Errors: -
  5. Check the state of the aggregates by using the storage aggregate show command.

    controller_A_1::> storage aggregate show
    Aggregate     Size Available Used% State   #Vols  Nodes            RAID Status
    --------- -------- --------- ----- ------- ------ ---------------- ------------
    ...
    aggr_b2    227.1GB   227.1GB    0% online       0 mcc1-a2          raid_dp, mirrored, normal...
  6. Heal the root aggregates by using the metrocluster heal -phase root-aggregates command.

    mcc1A::> metrocluster heal -phase root-aggregates
    [Job 137] Job succeeded: Heal Root Aggregates is successful

    If the healing is vetoed, you have the option of reissuing the metrocluster heal command with the -override-vetoes parameter. If you use this optional parameter, the system overrides any soft vetoes that prevent the healing operation.

  7. Verify that the heal operation is complete by using the metrocluster operation show command on the destination cluster:

    mcc1A::> metrocluster operation show
      Operation: heal-root-aggregates
          State: successful
     Start Time: 7/29/2016 20:54:41
       End Time: 7/29/2016 20:54:42
         Errors: -
  8. On the impaired controller module, disconnect the power supplies.